Project Management Professional (PMP) Exam Practice – Question2037

The project team is performing risk analysis. They are evaluating a risk that has a very high probability of occurring, and if it does it could cause the company to go out of business. Which of the following will the risk likely be analyzed with?


A.
Insurable risk
B. Qualitative Risk Analysis
C. Pure risk
D. Quantitative Risk Analysis

Correct Answer: D