The team on the router and switch upgrade project is involved in planning the project. They are performing Risk Response Planning. They are assigning risk owners. What is the main responsibility of the risk owner?


A.
Watching for additional risks on the project
B. Watching for risk triggers and telling the Project Manager if they happen
C. Letting the Project Manager know that the risk has happened
D. Implementing a risk response plan if the risk event occurs

Correct Answer: D