The Crosswind broadcasting has recently been awarded a large contract to create a new children's television show. This will require the company to move into a new office complete with production facilities 300% larger than what it presently has. The schedule is
tight for this new project, and there can be no delay. The new facility is behind schedule with the sets and production facilities on pace to finish two months late. The company is trying to use an incentive fee to motivate the provider of these services to complete
the work as quickly as possible even if it results in a smaller delay. This is an example of what type of risk response?


A.
Avoid
B. Accept
C. Transfer
D. Mitigate

Correct Answer: D