Project Management Professional (PMP) Exam Practice – Question2042

What type of contract provides the buyer with the most risk and seller the least risk?


A.
Fixed-price
B. Time and material
C. Cost-plus-fixed-fee
D. Cost-plus-percentage of cost

Correct Answer: D