Project Management Professional (PMP) Exam Practice – Question2043

The project will be using a company to provide the technicians for a national network upgrade project. Presently, the team is receiving proposals to select the vendor that will do the work. In what process is the team involved?


A.
Plan Contracting
B. Plan Purchases and Acquisitions
C. Select Sellers
D. Request Seller Responses

Correct Answer: D