Project Management Professional (PMP) Exam Practice – Question2044

The project will be using a company to provide the technicians for a national network upgrade project. Presently, the team is meeting with potential vendors, showing them more details associated with the work of the project, as well as answering any questions
they have about the work before their proposals are submitted. What is this called?


A.
Request Seller Responses
B. Bidders conference
C. Select Sellers
D. Request for information

Correct Answer: B