Project Management Professional (PMP) Exam Practice – Question2048

The project is in the phase of doing procurement audits. It is important to identify successes and failures of the procurement process. This identification is important for formal acceptance and closure. What process is the project in?


A.
Quality Assurance
B. Closing
C. Close Project
D. Contract Closure

Correct Answer: D