A project you have been managing is falling behind schedule. You have received approval to crash the project by adding an additional programmer. The cost you have negotiated is $60 US per hour. The programmer will work on the project until it is complete,
then the contract will end.
What type of contract is this?
A. Cost-plus
B. Purchase order
C. Time and materials
D. Fixed-price