Project Management Professional (PMP) Exam Practice – Question2050

You are the Project Manager for a national satellite rollout project. You are required to purchase and integrate reporting software for all the retail stores. As the Project Manager, you want one price from the vendors for the purchase and implementation of this
product. What type of document should be used?


A.
Invitation for bid
B. Request for quote
C. Request for proposal
D. Request for information

Correct Answer: C