A single-phase construction project is in the process of closing. There are a number of processes coming together as things finish up to complete the work of the project. Which of the following is correct?


A.
Contract Closure will come before Close Project
B. Close Project happens only if the project is completed as planned
C. Close Project and Contract Closure happen at the same time
D. Close Project will come before Contract Closure

Correct Answer: D