Project Management Professional (PMP) Exam Practice – Question2054

The retail chain will be using a vendor to provide engineers for a security camera network design and implementation. Presently, the team is determining the details needed for the documentation that will help select the company to provide the services. This also
includes evaluation criteria for comparing the proposals received. In what process is the team involved?


A.
Plan Purchases and Acquisitions
B. Plan Contracting
C. Request Sellers Responses
D. Select Sellers

Correct Answer: B