Project Management Professional (PMP) Exam Practice – Question2059

The contract is expected to cost $280K US. Actual costs are $240K US. There is a 50/50% share for any cost savings. What is the total value of the contract?


A.
$260K US
B. $240K US
C. $280K US
D. $300K US

Correct Answer: A