Project Management Professional (PMP) Exam Practice – Question2061

As a Project Manager, you are managing a project that has fourteen deliverables from outside vendors. One vendor has been in negotiations with a partner for more financing that could cause the vendor to stop production on one of your deliverables if they don?t
reach an agreement. A rumor is out that the vendor's plant will be shutting down because of this issue. What is the best course of action you should take?


A.
Contact the vendor and discuss this problem
B. Start contacting other vendors as a backup plan
C. Change vendors as soon as one is found
D. Initiate the risk response plan created for this vendor

Correct Answer: A