Project Management Professional (PMP) Exam Practice – Question2062

A team member has come to you and reported that the work due today is going to be five weeks late. The team member has requested that you do not report this to senior management. What is your professional and social responsibility to the project?


A.
Report the status accurately and timely
B. Issue a status report that does not contain this information
C. Wait until you have some good news to report with the bad news
D. The manager has helped you so you won't report the slip, hoping it gets back on schedule

Correct Answer: A