You are managing a project and the sponsor has removed the previous Project Manager on the project because they could not keep the project on budget. According to your current project budget, this project is over budget by $245,000. As the current Project
Manager, you are afraid you will also be removed if you report this status. What is the best response you can tell senior management?


A.
Report the delay to senior management and the reasons
B. Tell senior management the project is over budget by $245,000 with a plan to recover
C. The schedule is only two weeks behind so you don't report the delay
D. Don't report the delay and begin looking for a new job

Correct Answer: B