Project Management Professional (PMP) Exam Practice – Question2078

The sponsor is conducting a meeting and a Project Manager is reporting that his project is behind schedule by three weeks and under budget by $80K US. You discover from the PMO that the project is behind schedule by eight weeks and is over budget. What
should you do?


A.
Notify senior management
B. Report the Project Manager to PMI
C. Ask the PMO to investigate the project status
D. Review with the Project Manager how this status was produced

Correct Answer: D