Project Management Professional (PMP) Exam Practice – Question2080

A Project Manager has been assigned to manage a project to develop a reduced price desktop computer for a company that does not have this expertise. The project is three weeks behind schedule and under budget. After calculating the estimate at completion
(EAC), the Project Manager finds that project will be $34,589 under budget, but is expected to take four weeks longer than expected. What should the Project Manager do?


A.
Implement Gold Plating to make up for the difference
B. Bill for customer the total approved contracted amount
C. Report the current baseline project status and budget to the customer
D. Report the project status and budget to the customer

Correct Answer: D