Project Management Professional (PMP) Exam Practice – Question2083 A risk register that is part of the project management plan on a project would be viewed as what type of communication? A. Formal written B. Formal C. Verbal D. Contract Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question2082Project Management Professional (PMP) Exam Practice – Question2084