Project Management Professional (PMP) Exam Practice – Question2089

When you established the change control board for your avionics project, you established specific procedures to govern its operation. The procedures require all approved changes to baselines to be reflected in the______________.


A.
Performance measurement baseline
B. Change management plan
C. Quality assurance plan
D. Project management plan

Correct Answer: D

Explanation:

Explanation:
The project management plan must be updated changes to subsidiary plans and baselines subject to formal change control processes. Those changes must be communicated to appropriate stakeholders in a timely manner.