Project Management Professional (PMP) Exam Practice – Question2092

Facilitation techniques are used throughout project management. Your company is embarking on a project to completely eliminate defects in its products. You are the project manager for this project, and you are developing your project charter. To assist you,
which of the following facilitation techniques did you use?


A.
Surveys
B. Delphi approach
C. Meeting management
D. Focus groups

Correct Answer: C

Explanation:

Explanation:
Meeting management is an example of a facilitation technique used in developing the project charter as meetings may be held with key stakeholders and subject matter experts. Other facilitation techniques used to guide preparation of the charter are
brainstorming, problem solving, and conflict resolution.