Project Management Professional (PMP) Exam Practice – Question2094

You are managing a project in an organization is characterized by with rigid rules and policies and strict supervisory controls. Your project, sponsored by your CEO who is new to the company, is to make the organization less bureaucratic and more participative.
You are developing your project management plan. Given the organization as it now is set up, as you prepare your plan, you can use which of the following organizational process assets______________.


A.
Guidelines and criteria
B. Project management body of knowledge for your industry
C. Organizational structure and culture
D. The existing infrastructure

Correct Answer: B

Explanation:

Explanation:
While you are managing a different type of project, the organization has managed projects before and therefore may have as part of its organizational process assets a project management template, which sets forth guidelines and criteria to tailor the
organization’s processes to satisfy specific needs of the project.