You work for a telecommunications company, and when developing a project management plan for a new project, you found that you must tailor some company processes because the product is so different than those products typically produced by your
company. To tailor these processes, you will follow______________.
A. Standardized guidelines and work instructions
B. Stakeholder risk tolerances
C. Expert judgment
D. Structure of your company