Project Management Professional (PMP) Exam Practice – Question2098

An automated tool, project records, performance indicators, data bases, and financials are examples of items in______________.


A.
Organizational process assets
B. Project management information systems
C. Project management planning approaches
D. The tools and techniques for project plan development

Correct Answer: B

Explanation:

Explanation:
The items listed are part of these systems, a tool and technique in both processes.
PMI, PMBOK Guide, 2013, 84, 92