Project Management Professional (PMP) Exam Practice – Question2099

You realize that projects represent change, and on your projects, you always seem to have a number of change requests to consider. In your current project to manage the safety of the nation's cheese products and the testing methods used, you decided to
prepare a formal change management plan. An often overlooked type of change request is______________.


A.
Adding new subject matter experts to your team
B. Updates
C. Work performance information
D. Enhancing the reviews performed by your project's governance board

Correct Answer: B

Explanation:

Explanation:
Change requests may include corrective actions, preventive actions, defect repairs, or updates. Updates are changes to formally controlled project documents or plans to reflect modified or additional content.