You have been directed to establish a change control system for your company, but must convince your colleagues to use it. To be effective, the change control system must include______________.
A. Procedures that define how project documents may be changed
B. Specific change requests expected on the project and plans to respond to each one
C. Performance reports that forecast project changes
D. A description of the functional and physical characteristics of an item or system
A. Procedures that define how project documents may be changed
B. Specific change requests expected on the project and plans to respond to each one
C. Performance reports that forecast project changes
D. A description of the functional and physical characteristics of an item or system