Project Management Professional (PMP) Exam Practice – Question2101

You are working on the next generation of software for mobile phones for your telecommunications company. While time to market is critical, you know from your work on other projects that management reviews can be helpful and plan to use them on your
project. You are documenting them as part of your______________.


A.
Governance plan
B. Change management plan
C. Performance reviews
D. Project management plan

Correct Answer: D

Explanation:

Explanation:
The project management plan describes how the project will be executed and monitored and controlled. While it contains a number of subsidiary plans, it also contains other items including information on key management reviews for contents, their extent, and
timing to address open issues and pending decisions.