Project Management Professional (PMP) Exam Practice – Question2103

You are project manager for a systems integration effort and need to procure the hardware components from external sources. Your subcontracts administrator has told you to prepare a product description, which is referenced in a______________.


A.
Project statement of work
B. Contract scope statement
C. Request for proposal
D. Contract

Correct Answer: A

Explanation:

Explanation:
Project statement of work
The project statement of work describes in a narrative form the products, services, or results that the project will deliver. It references the product scope description as well as the business needs and the strategic plan.