Project Management Professional (PMP) Exam Practice – Question2104

Because your project is slated to last five years, you believe rolling wave planning is appropriate.
It provides information about the work to be done______________.


A.
Throughout all project phases
B. For successful completion of the current project phase
C. For successful completion of the current and subsequent project phases
D. In the next project phase

Correct Answer: C

Explanation:

Explanation:
Rolling wave planning provides progressive detailing of the work to be accomplished throughout the life of the project, indicating that planning and documentation are iterative and ongoing processes.