Project Management Professional (PMP) Exam Practice – Question2107

When closing a project, it is a best practice to______________.


A.
Update the project documents
B. Prepare a sustainment plan for the project's benefits
C. Measure product scope against the project management plan
D. Review the scope baseline

Correct Answer: D

Explanation:

Explanation:
In closing the project, it is necessary to ensure that the project work is completed, and the project has met its objectives. Since project scope is measured against the project management plan, the project manager then reviews the scope baseline to ensure
completion.
PMI, PMBOK Guide, 2013, 101