Project Management Professional (PMP) Exam Practice – Question2108

All the following are project baselines that are generally part of the project management plan EXCEPT______________.


A.
Technical

B. Scope
C. Time
D. Cost

Correct Answer: A

Explanation:

Explanation:
Scope, time, and cost are examples of project baselines to be part of the project management plan.