Project Management Professional (PMP) Exam Practice – Question2108 All the following are project baselines that are generally part of the project management plan EXCEPT______________. A. Technical B. Scope C. Time D. Cost Show Answer Hide Answer Correct Answer: A Explanation: Explanation: Scope, time, and cost are examples of project baselines to be part of the project management plan. Post navigation Project Management Professional (PMP) Exam Practice – Question2107Project Management Professional (PMP) Exam Practice – Question2109