Project Management Professional (PMP) Exam Practice – Question2109

You are responsible for a project management training curriculum that is offered throughout the organization. In this situation, your intangible deliverables are______________.


A.
Employees who can apply the training effectively
B. Training materials for each course
C. Certificates of completion for everyone who completes the program
D. The training curriculum as advertised in your catalog

Correct Answer: A

Explanation:

Explanation:
Most deliverables are tangible, such as buildings or roads, but intangible deliverables also can be provided. Work performance data are collected during direct and manage project work and is passed on to the controlling processes of each process area for further
analysis.