Project Management Professional (PMP) Exam Practice – Question2113

As you are working on your telecommunications project, even though you are using agile methods, you realize you are preparing an extensive amount of data and information. You regularly share data with your project team. Your last team meeting focused on the
number of change requests and also the start and finish dates of activities in your schedule. They are examples of______________.


A.
Key performance indicators
B. Work performance reports
C. Work performance data
D. Work performance information

Correct Answer: C

Explanation:

Explanation:
Work performance data are the raw observations and measurements identified during activities performed to carry out the work of the project. Other examples are the reported percent of work physically completed, quality and technical performance measures,
number of defects, actual costs, and actual durations.