Your project is proceeding according to schedule. You have just learned that a new regulatory requirement will cause a change in one of the project's performance specifications. To ensure that this change is incorporated into the project management plan, you
should______________.
A. Call a meeting of the change control board
B. Change the WBS, project schedule, and project plan to reflect the new requirement
C. Prepare a change request
D. Immediately inform all affected stakeholders of the new approach to take on the project