Different types of project phases are used on projects, and each phase culminates in the completion of at least one deliverable. The high-level nature of these phases means they are an element of the project life cycle. Some phases start before others complete.
If this approach is followed, it may result in______________.
A. An increase in the number of issues
B. Increasing the schedule
C. The need for a CCB
D. More rework
If this approach is followed, it may result in______________.
A. An increase in the number of issues
B. Increasing the schedule
C. The need for a CCB
D. More rework