Project Management Professional (PMP) Exam Practice – Question2118

Different types of project phases are used on projects, and each phase culminates in the completion of at least one deliverable. The high-level nature of these phases means they are an element of the project life cycle. Some phases start before others complete.
If this approach is followed, it may result in______________.


A.
An increase in the number of issues
B. Increasing the schedule
C. The need for a CCB
D. More rework

Correct Answer: D

Explanation:

Explanation:
The question is an example of an overlapping relationship between phases. It is used to compress the schedule through fast tracking as an example. By overlapping phases more resources may be needed, risks may increase, and more rework may result if a
significant phase progresses before accurate information is available from the previous phase.