Oftentimes when a project is terminated, senior managers will replace the project manager with an individual who is skilled in closing out projects. If this is done, the first step for the termination manager should be to______________.
A. Notify all relevant stakeholders of the termination
B. Complete the lessons learned report
C. Conduct an immediate review of the work packages
D. Review the status of all contracts
A. Notify all relevant stakeholders of the termination