Projects are supposed to succeed, not fail. However, termination is an option to consider when all but which one of the following conditions exist?


A.
The customer's strategy has changed.
B. There are new stakeholders.
C. Competition may make the project results obsolete.
D. The original purposes for the project have changed.

Correct Answer: B

Explanation:

Explanation:
As long as the new stakeholders agree with the project’s business case, the work should continue. However, if any of the other events occur, termination should be considered. Cleland and Ireland 2007, 365-375