Progressive elaboration of product characteristics on your project must be coordinated carefully with the______________
A. Proper project scope definition
B. Project stakeholders
C. Scope change control system
D. Customer's strategic plan
A. Proper project scope definition
B. Project stakeholders
C. Scope change control system
D. Customer's strategic plan