Project Management Professional (PMP) Exam Practice – Question2126

You and your project team recognize the importance of project scope management to a project's overall success; therefore, you include only the work required for successful completion of the project. The first step in the Project Scope Management process is
to______________


A.
Clearly distinguish between project scope and product scope
B. Prepare a scope management plan
C. Define and document your stakeholders' needs to meet the project's objectives
D. Capture and manage both project and product requirements

Correct Answer: B

Explanation:

Explanation:
The work involved in the six Project Scope Management processes begins by preparing a scope management plan, which is a subsidiary plan for the project management plan. It describes the Project Scope Management processes from definition to control.