Project Management Professional (PMP) Exam Practice – Question2128

You are managing a complex project for a new method of heating and air conditioning in vehicles. You will use both solar and wind technologies in this project to reduce energy costs. Therefore, you must ensure that the work of your project will result in delivering
the project's specified scope, which means that you should measure completion of the product scope against the______________


A.
Scope management plan
B. Project management plan
C. Product requirements
D. Requirements management plan

Correct Answer: C

Explanation:

Explanation:
Completion of the project scope is measured against the project management plan, and completion of the product scope is measured against the requirements. In the project context, product scope consists of features and functions that characterize the product,
service, or result. Project scope is the work that must be done to deliver the product, service, or result with specified features and functions.