Project Management Professional (PMP) Exam Practice – Question2132

The baseline for evaluating whether requests for changes or additional work are contained within or outside the project's exclusion is provided by the______________


A.
Project management plan
B. Project scope statement
C. Project scope management plan
D. WBS dictionary

Correct Answer: B

Explanation:

Explanation:
Project exclusion identifies generally what is included within the project, and state explicitly what is excluded from the project, if a stakeholder might assume that a particular product, service, or result could be a project component. Project boundaries are
described as part of the detailed project scope statement.