Project Management Professional (PMP) Exam Practice – Question2040

The Crosswind broadcasting has recently been awarded a large contract to create a new children's television show. This will require the company to move into a new office complete with production facilities 300% larger than what it presently has. The schedule is
tight for this new project, and there can be no delay. The new facility is behind schedule with the sets and production facilities on pace to finish two months late. The company is trying to use an incentive fee to motivate the provider of these services to complete
the work as quickly as possible even if it results in a smaller delay. This is an example of what type of risk response?


A.
Avoid
B. Accept
C. Transfer
D. Mitigate

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question2039

The team on the router and switch upgrade project is involved in planning the project. They are performing Risk Response Planning. They are assigning risk owners. What is the main responsibility of the risk owner?


A.
Watching for additional risks on the project
B. Watching for risk triggers and telling the Project Manager if they happen
C. Letting the Project Manager know that the risk has happened
D. Implementing a risk response plan if the risk event occurs

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question2038

The consulting company has created the scope of work for the project. They are in the process of creating a schedule and budget. They have added time into the schedule for the delays that always happen. They are also allocating money into the budget for more
computers and software that are usually needed beyond what is initially forecast. These items are an example of what?


A.
Unknown unknowns
B. Known unknowns
C. Risk management
D. Management reserve

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question2037

The project team is performing risk analysis. They are evaluating a risk that has a very high probability of occurring, and if it does it could cause the company to go out of business. Which of the following will the risk likely be analyzed with?


A.
Insurable risk
B. Qualitative Risk Analysis
C. Pure risk
D. Quantitative Risk Analysis

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question2034

The information technology system for the national power grid has been working well. Today, the main control processor crashed, disabling the west coast delivery of power to four states. Implementation of the risk response plan didn't fix the problem. Which of
the following steps would they perform first?


A.
Determine why the risk response plan failed
B. Fix the problem
C. Determine why the problem happened
D. Adjust the risk response plan

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question2033

The Project Manager and team are planning a banking software project. They are discussing what could go differently than planned on the project. They are also trying to identify warning signs that would show that these events could be on the verge of occurring.
What are these warning signs called?


A.
Risk analysis
B. Triggers
C. Problem solving
D. Risks

Correct Answer: B