Project Management Professional (PMP) Exam Practice – Question1042

How is quality control performed?


A.
By identifying quality standards that are relevant to the project and determining how to satisfy them
B. By monitoring specific project results in compliance with relevant quality standards and determining corrective actions as needed
C. By ensuring that the entire project team has been adequately trained in quality assurance processes
D. By applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question1038

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:


A.
Cost Plus Incentive Fee Contract (CPIF).
B. Cost Plus Fixed Fee Contract (CPFF).
C. Fixed Price Incentive Fee Contract (FPIF).
D. Time and Material Contract (T&M).

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question1036

Which baselines make up the performance measurement baseline?


A.
Scope baseline, cost baseline, and schedule baseline
B. Scope baseline, project management baseline, and quality baseline
C. Cost baseline, schedule baseline, and risk baseline
D. Cost baseline, project management baseline, and schedule baseline

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question1035

The three processes of Project Cost Management are:


A.
Estimate Costs, Control Schedule, and Control Costs.
B. Estimate Costs, Determine Budget, and Estimate Activity Resources.
C. Determine Budget, Control Schedule, and Estimate Activity Resources.
D. Estimate Costs, Determine Budget, and Control Costs.

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question1033

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?


A.
Cost Plus Fixed Fee Contract (CPFF)
B. Cost Plus Incentive Fee Contract (CPIF)
C. Firm Fixed Price Contract (FFP)
D. Fixed Price with Economic Price Adjustment Contract (FP-EPA)

Correct Answer: A