Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Project Management Professional (PMP) Exam Practice

Project Management Professional (PMP) Exam Practice – Question1032

Which of the following is a tool or technique used in the Determine Budget process?


A.
Variance analysis
B. Three-point estimating
C. Bottom-up estimating
D. Historical relationships

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 1032

Project Management Professional (PMP) Exam Practice – Question1031

Plan-do-check-act is also known as:


A.
prevention over inspection.
B. statistical sampling.
C. management responsibility.
D. continuous improvement.

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 1031

Project Management Professional (PMP) Exam Practice – Question1030

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:


A.
event.
B. response.
C. perception.
D. impact.

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 1030

Project Management Professional (PMP) Exam Practice – Question1029

The total of the planned value (PV) is also known as:


A.
work breakdown structure (WBS).
B. schedule target.
C. performance measurement baseline (PMB).
D. earned value baseline.

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 1029

Project Management Professional (PMP) Exam Practice – Question1028

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?


A.
Variance Analysis
B. Define Scope
C. Verify Scope
D. Control Scope

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 1028

Project Management Professional (PMP) Exam Practice – Question1027

The process to ensure that appropriate quality standards and operational definitions are used is:


A.
Plan Quality.
B. Perform Quality Assurance.
C. Perform Quality Control.
D. Total Quality Management.

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 1027

Project Management Professional (PMP) Exam Practice – Question1026

Administer Procurements is part of which Process Group?


A.
Planning
B. Executing
C. Monitoring and Controlling
D. Closing

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 1026

Project Management Professional (PMP) Exam Practice – Question1025

Which quality control technique illustrates the 80/20 principle?


A.
Ishikawa diagram
B. Control chart
C. Run chart
D. Pareto chart

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 1025

Project Management Professional (PMP) Exam Practice – Question1024

What happens to a stakeholder's project influence over time?


A.
Increases
B. Decreases
C. Stays the same
D. Has no bearing

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 1024

Project Management Professional (PMP) Exam Practice – Question1023

Which technique is utilized in the Control Schedule process?


A.
Performance measure
B. Baseline schedule

C. Schedule network analysis
D. Variance analysis

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 1023