Project Management Professional (PMP) Exam Practice – Question1022

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost
performance index?


A.
0.8
B. 0.89
C. 1.13
D. 1.25

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question1020

Which of the following events would result in a baseline update?


A.
A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.
B. A customer has approved a change request broadening the project scope and increasing the budget.
C. One of the risks identified in the risk management plan occurs, resulting in a schedule delay.
D. One of the key project team resources has left the team and no replacement is available.

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question1018

Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?


A.
Performance organizations
B. Schedule baselines
C. Work performance measurements
D. Change requests

Correct Answer: C

Project Management Professional (PMP) Exam Practice – Question1016

A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected
duration of the activity?


A.
Three weeks
B. Four weeks
C. Five weeks
D. Six weeks

Correct Answer: C