Project Management Professional (PMP) Exam Practice – Question0962

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?


A.
Estimate Costs
B. Control Costs
C. Plan Cost Management
D. Determine Budget

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 0962

Project Management Professional (PMP) Exam Practice – Question0961

Which term describes an assessment of correctness?


A.
Accuracy
B. Precision
C. Grade
D. Quality

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0961

Project Management Professional (PMP) Exam Practice – Question0960

Which items are an output of the Perform Integrated Change Control process?


A.
Work performance reports
B. Accepted deliverables
C. Project management plan updates
D. Organizational process assets

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0960

Project Management Professional (PMP) Exam Practice – Question0959

Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?


A.
Schedule network analysis
B. Reserve analysis
C. Alternative analysis
D. Variance analysis

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 0959

Project Management Professional (PMP) Exam Practice – Question0958

The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule performance index (5PI) for Task 4?


A.
0.83
B. 0.9
C. 1.11
D. 1.33

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0958

Project Management Professional (PMP) Exam Practice – Question0957

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost variance (CV) for Task 6?


A.
-2,000
B. 0
C. 1,000
D. 2,000

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 0957

Project Management Professional (PMP) Exam Practice – Question0956

The following chart contains information about the tasks in a project.

Based on the chart, what is the schedulevariance (SV) for Task 8?


A.
-2,000
B. -1,000
C. 1,000
D. 2,000

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 0956

Project Management Professional (PMP) Exam Practice – Question0955

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost performance index (CPI) for Task 2?


A.
0.8
B. 1
C. 1.25
D. 1.8

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0955

Project Management Professional (PMP) Exam Practice – Question0954

Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?


A.
Inspection
B. Quality audits
C. Design of experiments
D. Root cause analysis

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 0954

Project Management Professional (PMP) Exam Practice – Question0953

The chart below is an example of a:



A.
Responsibility assignment matrix (RAM)
B. Work breakdown structure (WBS)
C. RACI chart
D. Requirements traceability matrix

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 0953

Posts navigation

Older posts
Newer posts