Project Management Professional (PMP) Exam Practice – Question2011

The project is in a balanced matrix environment. There are significant challenges with the schedule and resource constraints of the project. Project personnel have been complaining to the Project Manager about the environment. In this type of environment, who
controls the resources?


A.
Functional Manager
B. Project Manager
C. Project Coordinator
D. Senior management

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question2010

The project has gone smoothly so far. The team members appear to be working with an end goal in mind and without a lot of supervision. They appear highly motivated and enjoying their work.
This is an example of what?


A.
Reward Theory
B. Theory Y environment
C. Motivation Theory
D. Theory X environment

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question2009

You are the Project Manager working with the customer on a construction project. You are required to purchase and integrate wireless communication system throughout the construction. A contract is signed with a vendor and work has begun. Halfway through
the project, the customer decides to upgrade the equipment. This change will require changes to the signed contract. Who has the authority to change the contract?


A.
Sponsor
B. Project Manager
C. Customer
D. Contract Administrator

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question2008

The project is in a projectized environment. There are significant challenges with meeting the tight schedule of the project and personnel leaving the company. Project personnel have been complaining to senior management about the environment hoping for a
resolution. In this type of environment, who controls the resources?


A.
Project Manager
B. Functional Manager
C. Senior management
D. Project Coordinator

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question2006

The electrical engineer has recently been promoted from lead engineer to section manager. In this new position, he will be responsible for managing projects and project resources. Over the five years he has been with the company, he was always ranked as one
of the top engineers but has had no formal project management training. This is an example of what?


A.
Halo Theory
B. Reward power
C. Problem solving
D. Equal opportunity employment

Correct Answer: A