Project Management Professional (PMP) Exam Practice – Question2002

The construction engineer is doing questionable work on his activities on the remodeling project. The Project Manager has spoken to him about it a few times to no resolution. Functional management has been made aware of this issue as well. Who is responsible
for the quality of the work of the construction engineer?


A.
Senior management
B. Functional management
C. The construction engineer
D. Project Manager

Correct Answer: C

Project Management Professional (PMP) Exam Practice – Question1999

The pilot for PM Airlines is in the process of flying from Dallas to Los Angeles. Adhering to the required pre-flight process, the pilot follows the procedures to ensure that he has properly selected and adjusted all the needed items to start up the plane for navigation.
Which of the following did he likely use?


A.
Process flowchart
B. Checklist
C. Cause and Effect diagram
D. Company policy

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question1998

The project is progressing. As the company starts to release the product of the project to market, the consumer isn't buying it as the company had projected. This appears to be because the company has released a lot of products before that had an excessive
number of defects. Who was ultimately responsible for these products being released with the defects?


A.
Functional management
B. Project Manager
C. The developer
D. Senior management

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question1996

The networking company that won the procurement contract has begun development of the work of the project. Given that they are trying to get additional business with the customer, they are providing some extra features and functionality. Which of the following
best describes this situation?


A.
This is Gold Plating and it is a good thing to help them get more business
B. This is Gold Plating and it is not a good practice
C. This was an unsuccessful negotiation on the behalf of the company that won the contract
D. This was a successful negotiation on the customer's behalf

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question1994

The printing company is putting a policy in place to use just-in-time manufacturing. It feels this policy will help minimize excess paper and ink costs and improve efficiency in processing and maximize square footage utilization. The amount of inventory needed for
this type of process is what?


A.
Minimal
B. 25%
C. Six Sigma
D. Zero

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question1993

The team is involved in defining what is needed to ensure project quality for their project. One team member says, "Do it right the first time." Another team member says, "Let's incorporate a method that reduces errors and helps the company make money." What
best describes this process?


A.
Kaizen
B. TQM
C. Fitness for Use
D. Zero Defects

Correct Answer: D