Project Management Professional (PMP) Exam Practice – Question0732

Which of the following correctly lists the configuration management activities included in the Integrated Change Control process?


A.
Configuration definition, configuration status accounting, configuration monitoring and control
B. Configuration identification, configuration status accounting, configuration verification and audit
C. Configuration identification, configuration status reporting, configuration verification and audit
D. Configuration definition, configuration status reporting, configuration monitoring and Control

Correct Answer: C

Project Management Professional (PMP) Exam Practice – Question0727

Which document describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results?


A.
Procurement management plan
B. Procurement statement of work
C. Request for proposal
D. Request for quote

Correct Answer: B