Project Management Professional (PMP) Exam Practice – Question0712

A process is defined as:


A.
A set of interrelated actions and activities performed to achieve a certain objective.
B. A set of guidelines that explains how to carry out a particular task.
C. The inputs for a task and the tools and techniques required to carry out the task.
D. A collection of logically related project activities, usually culminating in the completion of a major deliverable.

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question0710

The project manager for XYZ stationers is sequencing the activities for the project to set up a new office. It is known from knowledge of best practices that it is better to wait for the painters to finish painting the walls before the new floors are installed. This is an
example of which of the following types of dependency?


A.
Precedence
B. Discretionary
C. External
D. Mandatory

Correct Answer: B