Project Management Professional (PMP) Exam Practice – Question0682

Which of following could be organizational process assets?


A.
Historical information
B. Industry standards
C. Organization infrastructure
D. Marketplace conditions

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0682

Project Management Professional (PMP) Exam Practice – Question0681

What are assigned risk ratings based upon?


A.
Root cause analysis
B. Assessed probability and impact
C. Expert judgment
D. Risk Identification

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 0681

Project Management Professional (PMP) Exam Practice – Question0680

What is the tool and technique used to request seller responses?


A.
Procurement documents
B. Expert judgment
C. Bidder conferences
D. Contract types

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0680

Project Management Professional (PMP) Exam Practice – Question0679

A risk may be graded into different priorities by which process?


A.
Risk monitoring and controlling
B. Risk response planning
C. Qualitative risk analysis
D. Quantitative risk analysis

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0679

Project Management Professional (PMP) Exam Practice – Question0678

Which tool or technique measures performance of the project as it moves from project initiation through project closure?


A.
Resource leveling
B. Parametric measuring
C. Pareto chart
D. Earned value

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 0678

Project Management Professional (PMP) Exam Practice – Question0677

Which illustrates the connection between work that needs to be done and its project team members?


A.
Work breakdown structure
B. Network diagrams
C. Staffing management plan
D. Responsibility matrix

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 0677

Project Management Professional (PMP) Exam Practice – Question0676


Which of the following is the correct network diagram for the table?


A.
Begin-A-C-D-E-End-B-D
B. Begin-A-B-C-D-E-End
C. Begin-A-B-D-E-End A-C-D
D. Begin-A-C-D-E-End-B-C

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0676

Project Management Professional (PMP) Exam Practice – Question0675

Which of the following buffers protects the target finish date from slippage along the critical chain?


A.
Critical buffer
B. Project buffer
C. Duration buffer
D. Feeding buffer

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 0675

Project Management Professional (PMP) Exam Practice – Question0674

Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?


A.
Risk response planning
B. Manage stakeholders
C. Scope definition
D. Performance reporting

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 0674

Project Management Professional (PMP) Exam Practice – Question0673

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:


A.
Manage Stakeholder Expectations.
B. Monitor and Control Risks.
C. Plan Risk Management.
D. Report Performance.

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0673

Posts navigation

Older posts
Newer posts
Download all of these questions as Printable PDF for $19.50
Exam Practice Tests
sponsored